SEPTEMBER 2014
Renergen established.
JUNE 2015
Listed on the JSE’s AltX Exchange as first primary listed SPAC.
NOVEMBER 2015
Acquired Tetra4 and Windfall’s share of Côte d’Ivoire hydro electric joint venture (Mega Power Renewables). As a result of the acquisition, Renergen is no longer classified as a SPAC and is the first renewable energy company listed on AltX.
JANUARY 2016
Commenced construction of initial compression facilities for Tetra4.
MAY 2016
Tetra4 began production, supplying Compressed Natural Gas (CNG) to Megabus, a division of Unitrans Passenger Proprietary Limited Helium off-take agreement with Linde Group secured.
JUNE 2016
Commenced Front End Engineering and Design (FEED) for the helium liquefier.
SEPTEMBER 2016
Acquired control of Mega Power Renewables.
OCTOBER 2016
Reserve Update shows 24% increase in net reserve volumes.
MARCH 2017
Commenced FEED for the gas reticulation pipeline.
APRIL 2017
Completed and submitted the Environmental impact assessment (EIA) related to the gas pipeline reticulation network and construction of the helium facility to the competent authority for a Record of Decision (RoD) with no formal objections Continued progression of the feasibility study for Mega Power Renewables Côte d’Ivoire hydroelectric project.
MAY 2017
The EIA was submitted to the authority Renergen concludes R218 million funding with IDC.
SEPTEMBER 2017
Received a positive environmental authorisation or RoD on Tetra4’s Environmental Impact Assessment (EIA) by the Petroleum Agency of South Africa (PASA) 18 months of CNG production completed. Pipeline FEED completed LNG and helium liquefier FEED completed.
FEBRUARY 2018
Disposed of Mega Power Renewables.
MARCH 2018
Reserve Update shows 27% increase in net reserve volumes.
MAY 2018
CNG and LNG Offtake Agreement concluded with Anheuser-Busch InBev subsidiary, South African Breweries.
NOVEMBER 2018
R125 million raised in rights offer.
FEBRUARY 2019
US$40 loan facility approved by OPIC.
JUNE 2019
Listed on the ASX, raising AUD 10 million, which was twice the minimum. Selection of preferred EPC contractor for gas gathering system. Selection of preferred technology supply contractor for the LNG and LHe processing plant.
OCTOBER 2019
Second CNG filling station commissioned in JHB
NOVEMBER 2019
Consolidation of the Virginia Gas Project.
DECEMBER 2019
Gas strike with up to 12% helium recorded following successful sandstone drilling.