MILESTONE: Balance of plant

PARTY RESPONSIBLE

DATE

27 November 2019

MILESTONE ACHEIVED

TETRA4

EPCM

SENS announcement

WSCE

STATUS

ON TIME

MILESTONE: Site establishment for pipeline

PARTY RESPONSIBLE

DATE

15 December 2019

MILESTONE ACHEIVED

TETRA4

EPCM

announcement

WSCE

STATUS

ON TIME

MILESTONE: Design for pipeline completed

PARTY RESPONSIBLE

DATE

01 April 2020

MILESTONE ACHEIVED

TETRA4

EPCM

announcement

WSCE

STATUS

BEHIND SCHEDULE

MILESTONE: Design for plant completed

PARTY RESPONSIBLE

DATE

18 August 2020

MILESTONE ACHEIVED

TETRA4

EPCM

WSCE

announcement

STATUS

AHEAD OF SCHEDULE

MILESTONE: Plant batch 1 FOB

PARTY RESPONSIBLE

DATE

24 March 2021

MILESTONE ACHEIVED

TETRA4

EPCM

WSCE

STATUS

ON TIME

MILESTONE: Pipeline completed (Performance Testing)

PARTY RESPONSIBLE

DATE

30 May 2021

MILESTONE ACHEIVED

TETRA4

EPCM

WSCE

STATUS

Delayed by COVID-19

MILESTONE: Plant batch 2 FOB

PARTY RESPONSIBLE

DATE

14 April 2021

MILESTONE ACHEIVED

TETRA4

EPCM

WSCE

STATUS

ON TIME

MILESTONE: Site establishment for plant

PARTY RESPONSIBLE

DATE

24 July 2021

MILESTONE ACHEIVED

TETRA4

EPCM

WSCE

Joint Milestone

STATUS

Delayed by COVID-19

MILESTONE: Plant utilities commissioned (Electricity and Water)

PARTY RESPONSIBLE

DATE

14 December 2021

TETRA4

EPCM

Joint Milestone

WSCE

STATUS

Delayed by COVID-19

MILESTONE: Gas to plant (Commence Hot Commissioning)

PARTY RESPONSIBLE

DATE

14 December 2021

TETRA4

Joint Milestone

EPCM

WSCE

Joint Milestone

STATUS

STATUS

Delayed by COVID-19