MILESTONE: Plant batch 1 FOB
PARTY RESPONSIBLE
DATE
24 March 2021
MILESTONE ACHIEVED
TETRA4
EPCM
WSCE
STATUS
ON TIME
MILESTONE: Pipeline completed (Performance Testing)
PARTY RESPONSIBLE
DATE
30 May 2021
MILESTONE ACHIEVED
TETRA4
EPCM
WSCE
STATUS
Delayed by COVID-19
MILESTONE: Plant batch 2 FOB
PARTY RESPONSIBLE
DATE
14 April 2021
MILESTONE ACHIEVED
TETRA4
EPCM
WSCE
STATUS
ON TIME
MILESTONE: Site establishment for plant
PARTY RESPONSIBLE
DATE
24 July 2021
MILESTONE ACHIEVED
TETRA4
EPCM
WSCE
Joint Milestone
STATUS
Delayed by COVID-19
MILESTONE: Plant utilities commissioned (Electricity and Water)
PARTY RESPONSIBLE
DATE
14 December 2021
TETRA4
[elfsight_countdown_timer id=”7″]
EPCM
Joint Milestone
WSCE
STATUS
Delayed by COVID-19
MILESTONE: Gas to plant (Commence Hot Commissioning)
PARTY RESPONSIBLE
DATE
14 December 2021
TETRA4
Joint Milestone
EPCM
[elfsight_countdown_timer id=”8″]
WSCE
Joint Milestone
STATUS
STATUS
Delayed by COVID-19