MILESTONES

Status key (the date / status will reflect the status of the milestone. “On time” will mean up to 1 week earlier or later of the anticipated milestone date)

Ahead of schedule On time Behind schedule

MILESTONE

DATE / STATUS

TETRA4

EPCM

WSCE

Balance of Plant

27 Nov 19

Site establishment for pipeline

15 Dec 19

Design for pipeline completed

01 Apr 20

Site establishment for plant

15 Jun 20

Joint milestone

Design for plant completed

18 Aug 20

Plant batch 1 FOB

01 Nov 20

Pipeline completed

30 Nov 20

Joint milestone

Plant batch 2 FOB

01 Jan 21

Plant utilities commissioned

08 Apr 21

Joint milestone

Gas to plant

07 Jul 21

Joint milestone

Joint milestone

STATUS KEY (The DATE / STATUS will reflect the status of the milestone. On Time will mean up to 1 week earlier or later of the anticipated milestone date)

Ahead of Schedule On Time Behind Schedule

Balance of plant

DATE

27 Nov 19

EPCM

Site establishment for pipeline

DATE

15 Dec 19

EPCM

Design for pipeline completed

DATE

01 Apr 20

WSCE

Site establishment for plant

DATE

15 Jun 20

EPCM + WSCE

Design for plant completed

DATE

18 Aug 20

WSCE

Plant batch 1 FOB

DATE

01 Nov 20

WSCE

Pipeline completed

DATE

30 Nov 20

TETRA 4 + EPCM

Plant batch 2 FOB

DATE

01 Jan 21

T4

Plant utilities commissioned

DATE

08 Apr 21

TETRA 4 + EPCM

Gas to plant

DATE

07 Jul 21

TETRA 4 + EPCM + WSCE